NASA will likely delay by as much as a month some space shuttle launches scheduled for next year because of a backlog in processing the shuttles' external fuel tanks, an agency spokesman said Monday.
If approved, the revised schedule would push back the first launch of 2007 to March 16 from February 22; the launch of space shuttle Endeavour to June 28 from June 11; and the launch of Atlantis to September 7 from August 9. Two other flights carrying international space station parts constructed by the European and Japanese space agencies still are scheduled for later in 2007.
In the three years since the Columbia disaster, NASA's efforts to get the external fuel tanks ready for launch have been confounded by design changes and Hurricane Katrina, which damaged the tank assembly plant in New Orleans last year.
"The effects of Katrina are still being felt somewhat," NASA spokesman Kyle Herring said. "Getting back on track with the tank is obviously the biggest challenge there."
To discuss the space program and space exploration. Current space events, probes, missions etc. Also will focus on Moon and Mars programs, colonizing of space and Climate Change.
Tuesday, October 17, 2006
Shuttle delays
The Shuttle launch planned for the beginning of the year will be delayed. The manufacturing of the external tanks have been effected by good ol' hurricane Katrina from last year.
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment